= 18.13 — Foundations | |
== 18.13.1 Scope | |
=== 18.13.1.1 This section shall apply to foundations resisting | |
earthquake-induced forces or transferring earthquake induced | |
forces between structure and ground. | |
=== 18.13.1.2 The provisions in this section for piles, drilled | |
piers, caissons, and slabs-on-ground shall supplement other | |
applicable Code design and construction criteria, including | |
1.4.6 and 1.4.7. | |
== 18.13.2 Footings, foundation mats, and pile caps | |
=== 18.13.2.1 The provisions of this section shall apply to | |
structures assigned to SDC D, E, or F. | |
=== 18.13.2.2 Longitudinal reinforcement of columns and | |
structural walls resisting forces induced by earthquake | |
effects shall extend into the footing, mat, or pile cap, and | |
shall be fully developed for tension at the interface. | |
=== 18.13.2.3 Columns designed assuming fixed-end conditions | |
at the foundation shall comply with 18.13.2.2 and, | |
if hooks are required, longitudinal reinforcement resisting | |
flexure shall have 90-degree hooks near the bottom of the | |
foundation with the free end of the bars oriented toward the | |
center of the column. | |
= R18.13 — Foundations | |
== R18.13.1 Scope | |
Requirements for foundations supporting buildings | |
assigned to SDC C, D, E, or F represent a consensus of a | |
minimum level of good practice in designing and detailing | |
concrete foundations. However, because repairs to foundations | |
can be extremely difficult and expensive, it may be | |
desirable that the elements of the foundation remain essentially | |
elastic during strong ground motions. Methods to | |
achieve this goal include designing the foundation to include | |
an overstrength factor or an increased seismic demand level | |
when compared to the superstructure, or comparing strengths | |
to demands predicted by nonlinear response history analyses | |
with appropriate consideration of uncertainty in demands | |
(Klemencic et al. 2012). | |
== R18.13.2 Footings, foundation mats, and pile caps | |
=== R18.13.2.3 Tests (Nilsson and Losberg 1976) have | |
demonstrated that flexural members terminating in a footing, | |
slab, or beam (a T-joint or L-joint) should have their hooks | |
turned inward toward the axis of the member for the joint to | |
be able to resist the flexure in the member forming the stem | |
of the T or L. | |
American Concrete Institute – Copyrighted © Material – www.concrete.org | |
PART 5: EARTHQUAKE RESISTANCE 343 | |
18 Seismic | |
No further reproduction or distribution is permitted. | |
=== 18.13.2.4 Columns or boundary elements of special structural | |
walls that have an edge within one-half the footing | |
depth from an edge of the footing shall have transverse | |
reinforcement in accordance with 18.7.5.2 through 18.7.5.4 | |
provided below the top of the footing. This reinforcement | |
shall extend into the footing, mat, or pile cap a length equal | |
to the development length, calculated for fy in tension, of | |
the column or boundary element longitudinal reinforcement. | |
=== 18.13.2.5 Where earthquake effects create uplift forces in | |
boundary elements of special structural walls or columns, | |
flexural reinforcement shall be provided in the top of the | |
footing, mat, or pile cap to resist actions resulting from the | |
factored load combinations, and shall be at least that required | |
by 7.6.1 or 9.6.1. | |
=== 18.13.2.6 Structural plain concrete in footings and basement | |
walls shall be in accordance with 14.1.4. | |
=== 18.13.2.7 Pile caps incorporating batter piles shall be | |
designed to resist the full compressive strength of the batter | |
piles acting as short columns. The slenderness effects of | |
batter piles shall be considered for the portion of the piles | |
in soil that is not capable of providing lateral support, or in | |
air or water. | |
=== R18.13.2.4 Columns or boundary members supported | |
close to the edge of the foundation, as often occurs near | |
property lines, should be detailed to prevent an edge failure | |
of the footing, pile cap, or mat. | |
=== R18.13.2.5 The purpose of this section is to emphasize | |
that top reinforcement in footings, mats, and pile caps may | |
be required, in addition to other required reinforcement. | |
=== R18.13.2.6 Foundation and basement walls should be | |
reinforced in buildings assigned to SDC D, E, or F. | |
=== R18.13.2.7 Batter piles typically attract higher lateral | |
forces during earthquakes than vertical piles. Extensive | |
structural damage has been observed at the junction of batter | |
piles and building foundations. The pile cap and surrounding | |
structure should be designed for the potentially large forces | |
that can be developed in batter piles. | |
== 18.13.3 Grade beams and slabs-on-ground | |
=== 18.13.3.1 For structures assigned to SDC D, E, or F, grade | |
beams and beams that are part of a mat foundation subjected | |
to flexure from columns that are part of the seismic-forceresisting | |
system shall be in accordance with 18.6. | |
=== 18.13.3.2 For structures assigned to SDC C, D, E, or F, | |
slabs-on-ground that resist in-plane earthquake forces from | |
walls or columns that are part of the seismic-force-resisting | |
system shall be designed as diaphragms in accordance with | |
18.12. The construction documents shall clearly indicate that | |
the slab-on-ground is a structural diaphragm and part of the | |
seismic-force-resisting system. | |
== R18.13.3 Grade beams and slabs-on-ground | |
For earthquake conditions, slabs-on-ground (soil-supported | |
slabs) are often part of the lateral-force-resisting system and | |
should be designed in accordance with this Code as well as | |
other appropriate standards or guidelines (refer to 1.4.8). | |
=== R18.13.3.1 Grade beams resisting flexural stresses from | |
column moments should have reinforcement details similar | |
to the beams of the frame above the foundation. | |
=== R18.13.3.2 Slabs-on-ground often act as a diaphragm to | |
tie the building together at the ground level and minimize the | |
effects of out-of-phase ground motion that may occur over | |
the footprint of the building. The construction documents | |
should clearly state that these slabs-on-ground are structural | |
members so as to prohibit saw cutting of the slab. | |
== 18.13.4 Foundation seismic ties | |
=== 18.13.4.1 For structures assigned to SDC C, D, E, or F, | |
individual pile caps, piers, or caissons shall be interconnected | |
by foundation seismic ties in orthogonal directions, | |
unless it can be demonstrated that equivalent restraint is | |
provided by other means. | |
== R18.13.4 Foundation seismic ties | |
=== R18.13.4.1 The foundation seismic ties should sufficiently | |
interconnect foundations to act as a unit and be designed to | |
minimize the relative movement of an individual column or | |
tie relative to the foundation. This is essential where surface | |
soils are soft enough to require deep foundations or where | |
the site soils are susceptible to liquefaction. | |
American Concrete Institute – Copyrighted © Material – www.concrete.org | |
344 ACI 318-19: BUILDING CODE REQUIREMENTS FOR STRUCTURAL CONCRETE | |
No further reproduction or distribution is permitted. | |
=== 18.13.4.2 For structures assigned to SDC D, E, or F, individual | |
spread footings founded on soil defined in ASCE/SEI | |
7 as Site Class E or F shall be interconnected by foundation | |
seismic ties. | |
=== 18.13.4.3 Where required, foundation seismic ties shall | |
have a design strength in tension and compression at least | |
equal to 0.1SDS times the greater of the pile cap or column | |
factored dead load plus factored live load unless it is demonstrated | |
that equivalent restraint will be provided by (a), (b), | |
(c), or (d): | |
(a) Reinforced concrete beams within the slab-on-ground | |
(b) Reinforced concrete slabs-on-ground | |
(c) Confinement by competent rock, hard cohesive soils, | |
(d) Other means approved by the building official | |
=== 18.13.4.4 For structures assigned to SDC D, E, or F, grade | |
beams designed to act as horizontal foundation seismic ties | |
between pile caps or footings shall have continuous longitudinal | |
reinforcement that shall be developed within or beyond | |
the supported column or anchored within the pile cap or | |
footing at all discontinuities and shall satisfy (a) and (b): | |
(a) The smallest cross-sectional dimension of the grade | |
beam shall be at least equal to the clear spacing between | |
connected columns divided by 20, but need not exceed | |
(b) Closed tie transverse reinforcement shall be provided at | |
a spacing not to exceed the lesser of 0.5 times the smallest | |
orthogonal cross-sectional dimension and 300 mm. | |
=== R18.13.4.2 The ties between footings should have the same | |
characteristics as the ties between pile caps in R18.13.4.1. | |
=== R18.13.4.3 The minimum foundation seismic tie design | |
strength requirement based on a percentage of the factored | |
dead plus live load provides a minimum connection between | |
foundation elements. Other types of restraint can be used | |
if substantiated as equivalent to the minimum tie design | |
strength. The required design strength for the tie beam must | |
be at least equal to 0.1SDS times the larger force on either end | |
of the tie beam, and that force is from the column or pile cap, | |
whichever applies. | |
== 18.13.5 Deep foundations | |
=== 18.13.5.1 This section shall apply to the following types | |
(a) Uncased cast-in-place concrete drilled or augered piles | |
(b) Metal cased concrete piles | |
(c) Concrete filled pipe piles | |
(d) Precast concrete piles | |
=== 18.13.5.2 For structures assigned to SDC C, D, E, or F, | |
piles, piers, or caissons resisting tension loads shall have | |
continuous longitudinal reinforcement over their length to | |
resist design tension forces. | |
=== 18.13.5.3 For structures assigned to SDC C, D, E, or F, the | |
minimum longitudinal and transverse reinforcement required | |
by 18.13.5.7 through 18.13.5.10 shall be extended over the | |
entire unsupported length for the portion of deep foundation | |
member in air or water, or in soil that is not capable | |
of providing adequate lateral restraint to prevent buckling | |
throughout this length. | |
== R18.13.5 Deep foundations | |
Adequate performance of piles and caissons for earthquake | |
effects requires that these provisions be met in addition | |
to other applicable standards or guidelines (refer to | |
R1.4.7). | |
=== R18.13.5.3 Minimum reinforcement lengths for both | |
longitudinal and transverse reinforcement are based on | |
the assumption that soil is capable of providing lateral | |
support. For portions of the pile above ground, typically in | |
air or water, or where soil is not capable of providing this | |
lateral restraint, the minimum reinforced lengths should be | |
increased, and the member should be designed as a column. | |
American Concrete Institute – Copyrighted © Material – www.concrete.org | |
PART 5: EARTHQUAKE RESISTANCE 345 | |
18 Seismic | |
No further reproduction or distribution is permitted. | |
=== 18.13.5.4 For structures assigned to SDC C, D, E, or F, | |
hoops, spirals, and ties in deep foundation members shall be | |
terminated with seismic hooks. | |
=== 18.13.5.5 For structures assigned to SDC D, E, or F or | |
located in Site Class E or F, concrete deep foundation | |
members shall have transverse reinforcement in accordance | |
with 18.7.5.2, 18.7.5.3, and Table 18.7.5.4 Item (e) within | |
seven member diameters above and below the interfaces | |
between strata that are hard or stiff and strata that are liquefiable | |
or soft. | |
=== 18.13.5.6 For structures assigned to SDC D, E, or F, in | |
foundations supporting one- and two-story stud bearing wall | |
construction, concrete piles, piers or caissons, and foundation | |
ties are exempt from the transverse reinforcement | |
requirements of 18.13.5.3 through 18.13.5.5. | |
=== R18.13.5.5 During earthquakes, piles can be subjected to | |
high flexural and shear demands at points of discontinuity, | |
such as at interfaces between stiff and soft soil strata. ASCE/ | |
SEI 7 defines limits for soil strata. Transverse reinforcement | |
is required in these regions to provide ductile behavior. | |
In determining the portions of a pile with increased transverse | |
reinforcement, accommodations are often made to the | |
length of the reinforced zone for transverse reinforcement to | |
account for variations in the driven pile tip elevations and | |
variations in the interface elevations between stiff and soft | |
soil strata. | |
=== 18.13.5.7 Uncased cast-in-place drilled or augered | |
==== 18.13.5.7.1 For structures assigned to SDC C, D, E, or | |
F, reinforcement shall be provided in uncased cast-in-place | |
drilled or augered concrete piles where required by analysis | |
and in accordance with the requirements in Table 18.13.5.7.1. | |
=== R18.13.5.7 Uncased cast-in-place drilled or augered | |
==== R18.13.5.7.1 Longitudinal and transverse reinforcement | |
requirements prescribed by this section result in ductility | |
consistent with the applicable Seismic Design Category | |
(SDC) to withstand ground deformation that occurs during | |
earthquakes. | |
Where piles are subjected to significant uplift forces, the | |
longitudinal reinforcement length required by analysis may | |
exceed the minimum reinforcement length requirements. | |
Transverse reinforcement is required at the top of the pile | |
to provide ductile performance where flexural yielding can | |
potentially occur. For SDC D, E, and F and Site Classes A, | |
B, C, and D, one-half of the transverse reinforcement for | |
special moment frame columns is acceptable because some | |
level of confinement is attributed to competent soils. For Site | |
Class E and F, full column confinement is required because | |
the soils are either liquefiable or not considered competent | |
enough to provide confinement. | |
American Concrete Institute – Copyrighted © Material – www.concrete.org | |
346 ACI 318-19: BUILDING CODE REQUIREMENTS FOR STRUCTURAL CONCRETE | |
No further reproduction or distribution is permitted. | |
Table 18.13.5.7.1—Minimum reinforcement for uncased cast-in-place or augered concrete piles or piers | |
Minimum reinforcement_ | |
==== 18.13.5.7.2 Minimum longitudinal and transverse reinforcement | |
shall be provided along minimum reinforced | |
lengths measured from the top of the pile in accordance with | |
Table 18.13.5.7.1. | |
==== 18.13.5.7.3 Longitudinal reinforcement shall extend at least | |
the development length in tension beyond the flexural length of | |
the pile, which is defined in Table 18.13.5.7.1 as the distance | |
from the bottom of the pile cap to where 0.4Mcr > Mu. | |
==== R18.13.5.7.3 Reinforcement should extend ℓd beyond the | |
point where plain concrete is no longer adequate to resist the | |
factored moment. | |
=== 18.13.5.8 Metal-cased concrete piles | |
==== 18.13.5.8.1 For structures assigned to SDC C, D, E, or | |
F, longitudinal reinforcement requirements and minimum | |
reinforced lengths for metal-cased concrete piles shall be the | |
same as for uncased concrete piles in 18.13.5.7. | |
==== 18.13.5.8.2 Metal-cased concrete piles shall have a spiral-welded | |
metal casing of a thickness not less than 2 mm that | |
=== R18.13.5.8 Metal-cased concrete piles | |
==== R18.13.5.8.2 Spiral-welded metal casing with the specified | |
wall thickness provides confinement equivalent to | |
American Concrete Institute – Copyrighted © Material – www.concrete.org | |
PART 5: EARTHQUAKE RESISTANCE 347 | |
18 Seismic | |
No further reproduction or distribution is permitted. | |
==== R18.13.5.8.2 Continuation | |
closed ties or spirals required in an uncased concrete pile | |
and eliminates the need for confinement ties. | |
=== R18.13.5.9 Concrete-filled pipe piles | |
==== R18.13.5.9.1 For resistance to uplift forces, concrete bond | |
to the steel pipe is to be ignored in determining anchorage | |
of the pile. Concrete shrinkage can be detrimental to bond, | |
therefore shrinkage should be controlled, or force transfer | |
via other methods such as headed studs or surface irregularities | |
on the pipe should be considered. Reinforcement at the | |
top of the pile is extended into the pile cap to tie the elements | |
together and assist transfer of force to the pile cap. | |
=== R18.13.5.10 Precast concrete piles | |
==== R18.13.5.10.1 The potential for driving precast piles to a | |
tip elevation different than that specified in the construction | |
documents should be considered when detailing the pile. If | |
the pile reaches refusal at a shallower depth, a longer length | |
of pile will need to be cut off. If this possibility is not foreseen, | |
the length of transverse reinforcement required by | |
these provisions may not be provided after the excess pile | |
length is cut off. | |
==== R18.13.5.10.4(a) In a study of minimum confinement | |
reinforcement for prestressed concrete piles (Sritharan et al. | |
2016), the relationship between curvature ductility demand | |
==== 18.13.5.8.2 Continuation | |
is adequately protected from possible deleterious action due | |
to soil constituents, changing water levels, or other factors | |
indicated by boring records of site conditions. | |
=== 18.13.5.9 Concrete-filled pipe piles | |
==== 18.13.5.9.1 For structures assigned to SDC C, D, E or F, | |
concrete-filled pipe piles shall have longitudinal reinforcement | |
in the top of the pile with a total area of at least 0.01Ag | |
and with a minimum length within the pile equal to two times | |
the required embedment length into the pile cap, but not less | |
than the development length in tension of the reinforcement. | |
=== 18.13.5.10 Precast concrete piles | |
==== 18.13.5.10.1 For precast concrete driven piles, the length | |
of transverse reinforcement provided shall be sufficient to | |
account for potential variations in the elevation of pile tips. | |
==== 18.13.5.10.2 Precast nonprestressed concrete piles for | |
structures assigned to SDC C shall satisfy (a) through (d): | |
(a) Minimum longitudinal steel reinforcement ratio shall | |
be 0.01. | |
(b) Longitudinal reinforcement shall be enclosed within a | |
minimum of No. 10 closed ties or 10 mm diameter spirals, | |
for up to 500 mm diameter piles, and No. 13 closed ties | |
or 13 mm diameter spirals, for larger diameter piles. | |
(c) Spacing of transverse reinforcement within a distance | |
of 3 times the least cross-sectional dimension of the pile | |
from the bottom of the pile cap shall not exceed the lesser | |
of 8 times the diameter of the smallest longitudinal bar | |
and 150 mm. | |
(d) Transverse reinforcement shall be provided throughout | |
the length of the pile at a spacing not exceeding 150 mm. | |
==== 18.13.5.10.3 For structures assigned to SDC D, E, or | |
F, precast nonprestressed concrete piles shall satisfy the | |
requirements of 18.13.5.10.2 and the requirements for | |
uncased cast-in-place or augered concrete piles in SDC D, | |
E, or F in Table 18.13.5.7.1. | |
==== 18.13.5.10.4 For structures assigned to SDC C, precastprestressed | |
concrete piles shall satisfy (a) and (b): | |
(a) If the transverse reinforcement consists of spirals or | |
circular hoops, the volumetric ratio of transverse reinforcement, | |
ρs, in the upper 6 m shall not be less than that | |
American Concrete Institute – Copyrighted © Material – www.concrete.org | |
348 ACI 318-19: BUILDING CODE REQUIREMENTS FOR STRUCTURAL CONCRETE | |
No further reproduction or distribution is permitted. | |
==== 18.13.5.10.4 Continuation | |
calculated by Eq. (18.13.5.10.4a) or calculated from a | |
more detailed analysis by Eq. (18.13.5.10.4b): | |
| |
0.15 (fc'/fyt) ... (18.13.5.10.4a) | |
| |
0.04 (fc'/fyt)( 2.8 + (2.3Pu)/(fc' Ag) ) ... 18.13.5.10.4b) | |
| |
and fyt shall not be taken greater than 690 MPa. | |
(b) A minimum of one-half of the volumetric ratio of | |
spiral reinforcement required by Eq. (18.13.5.10.4a) or | |
Eq. (18.13.5.10.4b) shall be provided for the remaining | |
length of the pile. | |
==== 18.13.5.10.5 For structures assigned to SDC D, E, or F, | |
precast-prestressed concrete piles shall satisfy (a) through | |
(e) and the ductile pile region shall be defined as the length | |
of pile measured from the bottom of the pile cap to the point | |
of zero curvature plus 3 times the least pile dimension, but | |
not less than 10.5 m. If the total pile length in the soil is 10.5 | |
m or less, the ductile pile region shall be taken as the entire | |
length of the pile: | |
(a) In the ductile pile region, the center-to-center spacing | |
of spirals or hoop reinforcement shall not exceed the least | |
of 0.2 times the least pile dimension, 6 times the diameter | |
of the longitudinal strand, and 150 mm. | |
(b) Spiral reinforcement shall be spliced by lapping one | |
full turn, by welding, or by the use of a mechanical splice. | |
If spiral reinforcement is lap spliced, the ends of the spiral | |
shall terminate in a seismic hook. Mechanical and welded | |
splices of deformed bars shall comply with 25.5.7. | |
(c) If the transverse reinforcement consists of spirals, or | |
circular hoops, the volumetric ratio of transverse reinforcement, | |
ρs, in the ductile pile region shall not be less | |
than that calculated by Eq. (18.13.5.10.5a) or calculated | |
from a more detailed analysis by Eq. (18.13.5.10.5b), | |
and the required volumetric ratio shall be permitted to be | |
obtained by providing an inner and outer spiral. | |
| |
0.2 (fc'/fyt) ... (18.13.5.10.5) | |
| |
0.06 (fc'/fyt) ( 2.8 + (2.3 Pu)/(fc' Ag) ) ... (18.13.5.10.5b) | |
| |
and fyt shall not be taken as greater than 690 MPa. | |
(d) Outside of the ductile pile region, spiral or hoop reinforcement | |
shall be provided with a volumetric ratio not | |
less than one-half of that required within the ductile pile | |
==== R18.13.5.10.4 (a) Continuation | |
on prestressed piles and overall system ductility demand | |
was considered in the context of all soil profiles identified | |
in ASCE/SEI 7. It was concluded that Eq. (18.13.5.10.4b) | |
results in adequate deformation capacity for structures | |
assigned to SDC C. The factored axial force on a pile should | |
be determined from Eq. (5.3.1c) and Eq. (5.3.1g) with 5.3.7 | |
and 5.3.8 as applicable. | |
==== R18.13.5.10.5 Observed damage from earthquakes and | |
concerns about the accuracy of calculated pile demands have | |
led to prescriptive requirements for confinement of potential | |
yielding regions of piles. The required confinement is | |
intended to provide adequate ductility capacity for structures | |
assigned to SDC D, E, and F (Sritharan et al. 2016). | |
American Concrete Institute – Copyrighted © Material – www.concrete.org | |
PART 5: EARTHQUAKE RESISTANCE 349 | |
18 Seismic | |
No further reproduction or distribution is permitted. | |
==== 18.13.5.10.5 Continuation | |
region, and the maximum spacing shall be in accordance | |
with Table 13.4.5.6(b). | |
(e) If transverse reinforcement consists of rectangular | |
hoops and crossties, the total cross-sectional area of lateral | |
transverse reinforcement in the ductile region shall be the | |
greater of Eq. (18.13.5.10.5c) and Eq. (18.13.5.10.5d). | |
The hoops and crossties shall be equivalent to deformed | |
bars not less than No. 10 in size, and rectangular hoop | |
ends shall terminate at a corner with seismic hooks. | |
| |
Ash = 0.3 sbc (fc'/fyt) ( Ag/Ach -1.0 )( 0.5 + (1.4Pu)/(fc' Ag) ) | |
... (18.13.5.10.5c) | |
| |
Ash = 0.12 sbc (fc'/fyt) ( 0.5 + (1.4 Pu)/(fc'Ag) ) | |
... (18.13.5.10.5d) | |
| |
and fyt shall not be taken as greater than 690 MPa. | |
==== 18.13.5.10.6 For structures assigned to SDC C, D, E, or | |
F, the maximum factored axial load for precast prestressed | |
piles subjected to a combination of earthquake lateral force | |
and axial load shall not exceed the following values: | |
(a) 0.2fc′Ag for square piles | |
(b) 0.4fc′Ag for circular or octagonal piles | |
==== R18.13.5.10.6 The axial load in precast prestressed piles is | |
limited to preclude spalling of the concrete cover prior to the | |
pile section experiencing flexural cracking, as this will result | |
in a significant loss in pile resistance (Sritharan et al. 2016). | |
== 18.13.6 Anchorage of piles, piers, and caissons | |
=== 18.13.6.1 For structures assigned to SDC C, D, E, or F, | |
the longitudinal reinforcement in piles, piers, or caissons | |
resisting tension loads shall be detailed to transfer tension | |
forces within the pile cap to supported structural members. | |
=== 18.13.6.2 For structures assigned to SDC C, D, E, or F, | |
concrete piles and concrete filled pipe piles shall be connected | |
to the pile cap by embedding the pile reinforcement in the | |
pile cap a distance equal to the development length or by the | |
use of field-placed dowels anchored in the concrete pile. For | |
deformed bars, the compression development length is used | |
if the pile is in compression. In the case of uplift, the tension | |
development length is used without reduction in length for | |
excess reinforcement. | |
=== 18.13.6.3 For structures assigned to SDC D, E, or F, if | |
tension forces induced by earthquake effects are transferred | |
between pile cap or mat foundation and precast pile by reinforcing | |
bars grouted or post-installed in the top of the pile, | |
the grouting system shall have been demonstrated by testing | |
to develop at least 1.25fy of the bar. | |
== R18.13.6 Anchorage of piles, piers, and caissons | |
=== R18.13.6.1 A load path is necessary at pile caps to transfer | |
tension forces from the reinforcing bars in the column or | |
boundary element through the pile cap to the reinforcement | |
of the pile or caisson. Examples of different types of pile | |
connections to pile caps are available in ASCE/COPRI Standard | |
for the Seismic Design of Piers and Wharves (61-14). | |
=== R18.13.6.2 Development length is determined according | |
to requirements of Chapter 25. Reductions in development | |
length for calculated stresses less than fy are not permitted, | |
as indicated in 25.4.10.2. Full development of the pile longitudinal | |
reinforcement into the pile cap is intended to enable | |
the capacity of the pile to pile cap connection to meet or | |
exceed the pile section strength. | |
=== R18.13.6.3 Grouted dowels in a blockout in the top of a | |
precast concrete pile need to be developed, and testing is | |
a practical means of demonstrating strength. Alternatively, | |
reinforcing bars can be cast in the upper portion of the pile, | |
exposed by chipping of concrete and mechanically spliced | |
or welded to an extension. | |
[ Lanjut Ke 18.14—Members not designated as part of the seismic-force-resisting system ... ] | |
| |
| |